Detail of AllinOne Repair Footing for Pier and Beam Structure
-- Sub-flooring supported by floor joists -- Beam/sill supports floor joists and rests on the pier cap -- Metal strap is nailed to the beam/sill and placed into the wet concrete -- 10" concrete sonotube formed column pier cap (see picture below)
-- 24" x 24" x 12" concrete pad*
* Concrete pad is built 24" below the soil grade.
-- Sonotube pier cap reinforced with steel cage of #4 rebar secured with metal ties*
-- Concrete pad reinforced with six #4 rebar secured with metal ties*
* All steel/rebar is new billet steel bars grade 40 or better * All concrete is 5 sac mix with minimum 28 day compressive strength of 2,500 lbs/in² |
|